Gotthard Base Tunnel

The Gotthard Base Tunnel (GBT) is a railway tunnel in the heart of the Swiss Alps expected to open in 2016. With a route length of Шаблон:Convert and a total of Шаблон:Convert of tunnels, shafts and passages, it is the world's longest rail tunnel, surpassing the Seikan Tunnel in Japan.

Its main purpose is to increase total transport capacity across the Alps, especially for freight, notably between Germany and Italy, and more particularly to shift freight volumes from road to rail to reduce environmental damage caused by ever-increasing numbers of heavy lorries. A secondary benefit will be to cut the journey time for passenger trains from Zürich to Milan by about an hour and from Zürich to Lugano to 1-hour 40 minutes.

The project consists of two single-track tunnels. It is part of the AlpTransit project, also known as the New Railway Link through the Alps (NRLA), which includes the Lötschberg Base Tunnel between the cantons of Bern and Valais and the under construction Ceneri Base Tunnel (scheduled to open late 2019) to the south. It bypasses the Gotthardbahn, a winding mountain route opened in 1882 across the Saint-Gotthard Massif, which is now operating at capacity, and establishes a direct route usable by high-speed rail and heavy freight trains.

After 64 percent of Swiss voters accepted the AlpTransit project in a 1992 referendum, tunnel construction began in 1996. Drilling operations in the eastern tunnel were completed on 15 October 2010 in a breakthrough ceremony broadcast live on Swiss TV, and in the western tunnel on 23 March 2011. AlpTransit Gotthard Ltd. will hand over the tunnel to Swiss Federal Railways (SBB) in operating condition in December 2016. Total cost of the project is 9.8 billion Swiss francs, or US$10.3 billion.

The two portals are near the villages of Erstfeld, Uri, and Bodio, Ticino. Nearby are two other St. Gotthard Tunnels: the 1881 Gotthard Rail Tunnel and the 1980 Gotthard Road Tunnel.

When completed, the Gotthard Base Tunnel will be one of the longest tunnel construction projects in the world: 20 years of constant construction and preperation.

Background

The route over the Gotthard Pass (or through its tunnels) is one of the most important passages through the Alps on the north-south axis. Traffic has increased more than tenfold since 1980 and the existing tunnels are at their capacity limits. A second (proposed) tunnel was to be constructed only if the volume of traffic rose above one million vehicles a year. In fact, the engineer Giovanni Lombardi, responsible for the construction of the road tunnel added, "one year after the inauguration, the tunnel was already seeing 2.5 million vehicles [today (23 October 2011) – about six million] annually. But the promise was forgotten".

To provide a faster and flatter passage through the Swiss Alps, the GBT cuts through the Gotthard Massif some Шаблон:Convert below the older tunnel. On the current track, the Gotthardbahn, only trains up to Шаблон:Convert when using two locomotives or up to Шаблон:Convert with an additional bank engine at the end of the train are able to pass through the narrow mountain valleys and through spiral tunnels climbing up to the portals of the old tunnel at a height of Шаблон:Convert above sea level.

When completed, standard freight trains of up to Шаблон:Convert will be able to pass this natural barrier. Because of ever-increasing international truck traffic, the Swiss voted in February 1994 for a shift in transportation policy (Traffic Transfer Act, enacted in October 1999).

The goal of both the laws (and the goal of the GBT, which is one of the means by which the law will achieve its objective) is to transport trucks, trailers and freight containers between southern Germany and northern Italy by rail to relieve the overused roads (intermodal freight transport and so-called rolling highway where the entire truck is transported) and to meet the political requirement of shifting as much tonnage as possible from truck transport to train transport, as required by the 'Alpine Protection Act' of 1994.

Passenger trains will be able to travel up to Шаблон:Convert through the GBT, reducing travel times for trans-Alpine train journeys by 50 minutes, and by one hour once the adjacent Zimmerberg and Ceneri Base Tunnels are completed.

Construction

AlpTransit Gotthard AG is responsible for construction. It is a wholly owned subsidiary of the Swiss Federal Railways (SBB-CFF-FFS).

To cut construction time in half, four access tunnels were built so that construction could start at four (a fifth was added later) different sites simultaneously (Erstfeld, Amsteg, Sedrun, Faido and Bodio).

The two tunnels are joined approximately every Шаблон:Convert by connecting galleries.

Trains can swap tunnels in the two multifunction stations (MFS) at Sedrun and Faido.

These stations will house ventilation equipment and technical infrastructure and will serve as emergency stops and evacuation routes upon tunnel completion.

Access to the Sedrun station site is by a level access tunnel Шаблон:Convert long from the valley floor near Sedrun, at the end of which two vertical shafts lead Шаблон:Convert down to the base tunnel level.

A proposal to construct a functioning railway station called Porta Alpina at this site was ruled out because of the small population served and the reduction in line capacity that would be caused by trains stopping there.

The final breakthrough in the east tube occurred on Friday 15 October 2010 at 14:17 +0200. The final breakthrough in the west tube occurred on Wednesday 23 March 2011 at 12:20.

On 16 December 2013, the operational test phase started on a 13 kilometer stretch in the southern section of the west tube between Faido and Bodio. Its purpose is to test the infrastructure and any anxilliary systems.

Allocation of work

The contracts were awarded in sections:

  • Erstfeld (the Шаблон:Convert section from Erstfeld to Amsteg), with two tunnel boring machines (TBM) boring the two tubes. The break-through of the east tube between Erstfeld and Amsteg took place 15 June 2009. The portal area was surface-mined, and drilling and blasting for the two branches is complete.
  • Amsteg (the Шаблон:Convert section from Amsteg to north of Sedrun), ARGE AGN (Strabag and Züblin Murer) received the contract for work in this sector. On 9 December 2009, the Amsteg section was officially delivered to the owner for fitting-out. Civil engineering, construction, concrete and lining work are complete.
  • Sedrun (the Шаблон:Convert East tube and Шаблон:Convert West tube in the section immediately north and south of Sedrun), along with work performed by Transco (Bilfinger, Implenia, Frutiger and Pizzarotti). The final breakthrough in the west tube occurred in March 2011. Civil engineering construction, concreting and lining work are complete on Sedrun North. The northbound tubes from Amsteg to the Sedrun multifunction station (north) were handed over to the railway systems contractor Transtec Gotthard on 15 September 2011, the date specified in the construction schedule.
  • Faido (Шаблон:Convert East tube and Шаблон:Convert West tube in the section from south of Sedrun to Faido), with Consorzio TAT (Alpine Mayreder Bau, CSC Impresa costruzioni, Hochtief and Implenia and Impregilo) performing work.
  • Bodio (a Шаблон:Convert East tube and Шаблон:Convert West tube in the section from Faido to Bodio), with work performed by Consorzio TAT (Alpine Mayreder Bau, CSC Impresa costruzioni, Hochtief, Implenia and Impregilo). Civil engineering construction, concrete and lining works are complete.


Specifications

  • Length:
  • Total length of all tunnels and shafts: Шаблон:Convert
  • Diameter of each of the single-track tubes: Шаблон:Convert
  • Distance between cross passage tunnels: ca. Шаблон:Convert
  • Maximum overburden: Шаблон:Convert
  • Start of construction: 1993 (sounding drills), 1996 (preparations), 2003 (mechanical excavation)
  • End of construction: 2016
  • Commissioning: May 2016
  • Total cost: CHF 9.74 billion (Шаблон:As of) (US$10.1 billion)
  • Trains per day: 200–250
  • Electrification System: 15 kV, 16.7 Hz
  • Safety rules: The safety requirements on the rolling stock will be similar to other long Swiss tunnels, like possibility to override the emergency brake. This is in contrast to the Channel Tunnel which has several unique safety rules requiring custom made trains.
  • Amount of excavated rock: Шаблон:Convert, (Шаблон:Convert, the equivalent of 5 Giza pyramids)
  • Number of tunnel boring machines (TBM): Four Herrenknecht Gripper TBMs — Machine numbers S-210 and S-211 operated northbound from Bodio to Faido and Sedrun and were nicknamed Sissi and Heidi respectively; Machines S-229 and S-230 operated southbound from Erstfeld to Sedrun and were known as Gabi I and Gabi II.
  • 2004–2011 tunnel excavation:
Year   Month   Total excavated
kilometres miles percent
2004 July Шаблон:Convert 34.1
2005 June Шаблон:Convert 48.6
2006 June Шаблон:Convert 61.3
2007 June Шаблон:Convert 67.6
2008 March Шаблон:Convert 70.4
April Шаблон:Convert 71.0
July Шаблон:Convert 73.8
August Шаблон:Convert 75.1
October Шаблон:Convert 77.2
2009 January Шаблон:Convert 81.6
March Шаблон:Convert 83.9
May Шаблон:Convert 86.3
June Шаблон:Convert 87.6
July Шаблон:Convert 87.9
August Шаблон:Convert 90.0
September Шаблон:Convert 90.4
October Шаблон:Convert 91.3
November Шаблон:Convert 92.2
December Шаблон:Convert 93.0
2010 1 January Шаблон:Convert 93.4
1 February Шаблон:Convert 93.8
1 March Шаблон:Convert 94.7
1 April Шаблон:Convert 95.4
1 May Шаблон:Convert 95.8
1 June Шаблон:Convert 96.2
1 July Шаблон:Convert 96.6
1 August Шаблон:Convert 97.0
1 September Шаблон:Convert 97.5
1 October Шаблон:Convert 98.2
1 November Шаблон:Convert 98.7
1 December Шаблон:Convert 99.0
2011 1 January Шаблон:Convert 99.1
1 February Шаблон:Convert 99.3
1 March Шаблон:Convert 99.6
1 April Шаблон:Convert 99.91
1 May Шаблон:Convert 99.94
1 June Шаблон:Convert 99.99
1 July Шаблон:Convert 100

See also

  • List of tunnels by length
  • List of tunnels by location

References

Шаблон:Reflist

External links

Шаблон:Commons category

Listed in the following categories:
Post a comment
Tips & Hints
Arrange By:
There are no tips nor hints for Gotthard Base Tunnel yet. Maybe be you will be the first one to post useful information for fellow travellers? :)

Hotels nearby

See all hotels See all
The Chedi Andermatt Hotel

starting $842

Catrina Resort

starting $107

Hotel Badus

starting $92

Alpenhotel Schlüssel

starting $98

Gasthaus Skiklub

starting $132

Andermatt Swiss Alps Resort

starting $281

Recommended sights nearby

See all See all
Add to wishlist
I've been here
Visited
Teufelsbrücke

The Teufelsbrücke ('Devil's Bridge') is a bridge over the Schöllenen G

Add to wishlist
I've been here
Visited
Lago di Luzzone

Lago di Luzzone is a lake in Ticino, Switzerland. The reservoir has a

Add to wishlist
I've been here
Visited
St. Gotthard Pass

St. Gotthard Pass (italiano. San Gottardo) (el. 2108 m.) is a high

Add to wishlist
I've been here
Visited
Meierturm

Meierturm is a medieval tower in the municipality of Silenen in the

Add to wishlist
I've been here
Visited
Arnisee

Arnisee is a lake in the Canton of Uri, Switzerland. The reservoir can

Add to wishlist
I've been here
Visited
Lepontine Alps

The Lepontine Alps are a mountain range in the central part of the

Add to wishlist
I've been here
Visited
Castello di Brolio

The Castello di Brolio is a rural castle, palace and gardens located

Add to wishlist
I've been here
Visited
Hospental Castle

Hospental Castle or Langobarden Tower is a ruined medieval castle in

Similar tourist attractions

See all See all
Add to wishlist
I've been here
Visited
Royal Gorge Route Railroad

The Royal Gorge Route Railroad is a heritage railroad located in

Add to wishlist
I've been here
Visited
Manitou and Pike's Peak Railway

The Manitou and Pike's Peak Railway (also known as the Pikes Peak Cog

Add to wishlist
I've been here
Visited
Georgetown Loop Railroad

The Georgetown Loop Railroad is a Шаблон:RailGauge narrow gauge herit

Add to wishlist
I've been here
Visited
Flåm Line

The Flåm Line (Norwegian: Flåmsbana) is a 20.2-kilometer (12.6 mi) lo

Add to wishlist
I've been here
Visited
Niles Canyon Railway

The Niles Canyon Railway (NCRy) is a heritage railway running through

See all similar places